Interest for delay
Also called delay interest, delayed possession interest, delayed possession charges
Interest a developer must pay, for every month of delay, to a buyer who stays in a project after the possession date in the agreement for sale has passed.
Section 18, Real Estate (Regulation and Development) Act, 2016
Section 18 of the Real Estate (Regulation and Development) Act, 2016 gives the buyer a choice when the developer fails to hand over the flat on time. The buyer can withdraw and get a refund with interest and compensation, or stay and receive interest for each month until possession.
State rules set the rate. Maharashtra’s is the State Bank of India’s highest marginal cost of lending rate plus 2%, and under the Act a developer charges a buyer who pays late at the same rate. The buyer claims it through a complaint to the state regulator.