Interest for delay

Also called delay interest, delayed possession interest, delayed possession charges

Interest a developer must pay, for every month of delay, to a buyer who stays in a project after the possession date in the agreement for sale has passed.

Section 18, Real Estate (Regulation and Development) Act, 2016

Section 18 of the Real Estate (Regulation and Development) Act, 2016 gives the buyer a choice when the developer fails to hand over the flat on time. The buyer can withdraw and get a refund with interest and compensation, or stay and receive interest for each month until possession.

State rules set the rate. Maharashtra’s is the State Bank of India’s highest marginal cost of lending rate plus 2%, and under the Act a developer charges a buyer who pays late at the same rate. The buyer claims it through a complaint to the state regulator.

Read in full How to file a complaint against a developer with MahaRERA

Back to the glossary

Ask the desk

What are you looking for?

Fill in the sentence and set the slider. A Proprty Ctrl consultant reads it, checks the current figures for the area and contacts you.

  • A consultant reads every enquiry.
  • We use current registration and rent data for your area.
  • We contact you about this enquiry only, in the way you choose.

I want to in near , and I want to move .

Around ₹1 crore
How should we reach you?