Construction-linked payment plan
Also called CLP, construction-linked plan
A payment schedule for an under-construction flat in which each instalment falls due when the building reaches a set stage, such as a slab or the plastering.
Under Section 13(1) of the Real Estate (Regulation and Development) Act, 2016 (RERA), the developer can take no more than 10% of the cost before a registered agreement for sale, which then fixes the stages. Before paying a demand, match it with the quarterly progress update the developer must post on the RERA website under Section 11(1).
A home loan on this plan is released in stages, and interest runs only on the amount paid out so far. When construction slows, the demands slow with it, which is the plan’s main protection for the buyer.